Skip to content .

Pile of paperwork

On Site Power Generation

16 June 2008

Given the current push for a 60% reduction in carbon emissions by 2050 and the need for all new buildings to become zero carbon in the foreseeable future, there has been a lot of debate as to how to achieve this. A major aspect of the debate has been whether it is appropriate for local authorities to insist that a fixed percentage of the energy needs of a new development must be generated by on site renewable energy, rather than simply taking electricity from a supplier in the usual way. For intensive energy users this can pose a real problem, partly if the site is not suitable for some of the more common renewable energy technologies (such as wind and solar), and partly because of the sheer amount of energy they may have to generate.

The Merton Rule and PPS1

Merton Borough Council started the policy of requiring new developments to provide 20% of its energy needs from on site renewable energy and 140 Councils have now followed suit. There was concern, however, that some sites simply were not suitable for renewable energy generation and on 13 December 2007 the Government published a national planning policy statement (PPS1) which said that renewable energy quotas for new development must be flexible and only used where they are viable. PPS1 was supportive of off site provision, for example, through community energy schemes.

The Planning and Energy Bill

In the meantime, a private members bill called the Planning and Energy Bill was introduced into Parliament in December 2007 to support the Merton Rule by formally giving local authorities the power to require 10% on site renewable energy provision for new development. It was scheduled for its second reading in the House of Lords on 13 June 2008.

Citiworks (Energy) [2008] EUECJ C-439/06

A new spanner has been thrown into the works by this German case which came before the European Court of Justice of the European Communities on 22 May 2008.   EU Directive 2003/54 establishes common rules for the generation, transmission, distribution and supply of electricity. Recital 4 to the Directive states that all consumers should be free to chose their suppliers and all suppliers able to freely deliver to their customers. Recital 7 states that "non-discriminatory access to the network of the transmission or distribution system operator is of paramount importance".   

The EU Directive was transposed into German law by the EnWG. The EnWG states that operators of energy supply systems shall grant anyone access to its system without discrimination.  However, the EnWG contained provisions that the rules under the EnWG would not apply to a site network. There were various ways in which site network status could be claimed, and one was that the energy supply system is located on a geographically connected zone and serves predominantly its own supply purposes and those of connected undertakings.

The case involves Leipzig airport. FLH operates the airport and maintains an energy supply system to meet its own electricity requirements and those of 93 other undertakings located on the airport site. FLH claimed that as the electricity supply system was a site network, it did not have to grant access to third parties such as Citiworks to its supply system. The regulatory authority agreed, but that decision was challenged by Citiworks who claimed that EnWG was incompatible with Directive 2003/54.

The Court found that the Directive does not permit a national law which allows certain operators of energy supply systems to be exempt from having to allow open access to their energy supply system. The Directive itself contains certain exemptions but none of them applied in this case.

Conclusion

This case would suggest that if you operate a system that transmits electricity, unless you can fall within the limited exceptions set out in the Directive, you must allow third parties access to your energy supply system. This does not sit at all well alongside the proposed UK obligation for certain developments to have to generate and use their own energy as in fact under the Directive they should have a free choice of where they obtain their energy from and who they supply the energy that they generate to.

In the UK, there is an exemption from the electricity licensing rules (Electricity (Class Exemptions from the requirement for a licence) Order 2001) for a generator that supplies its entire generation output to a single consumer occupying premises located on the same site as the generating station. In addition, consumers normally have the right to change suppliers on 28 days notice, but this does not apply where the supplier is exempt from the need to hold a licence. It remains to be seen whether these rules in the UK, which effectively create a monopoly where power is generated on site, will remain valid given this latest ECJ judgement. If they prove to be invalid, this may spell the end of the Merton Rule.

OFGEM and BERR are currently consulting on reforming licensing regulations for decentralised energy systems in the UK to create more flexibility in the market.  However, they were waiting for the outcome of the Citiworks case before reaching any conclusions.

Contacts

Sarah Youren

Search all publications by type


Related locations